Work continues to move Carroll Township houses
Latest News, Main
July 7, 2025

Work continues to move Carroll Township houses

By TAYLOR BROWN, Senior Reporter 

The original project was halted after failing to meet the township’s setback requirements.

Work on two homes in Carroll Township has continued without any new hiccups.

Construction of the two homes by Black Lotus Group has become a regular point of discussion among residents who live in the Irey Plan neighborhood.

The homes that sit at the corner of Briarwood and Cedarwood drives will eventually be moved to fit inside setback requirements, but permits have not yet been issued for that work.

Though new permits have been granted and inspections have come back without any issues as previous issues are remediated, neighbors continue to have questions as the project moves forward to make sure history doesn’t repeat itself when it comes to the construction of the properties.

It’s been a bit of a contentious topic in the township that came to a head last fall when residents again brought their concerns about the property’s setback requirements to the board of supervisors.

Work came to a halt in mid-December after an independent survey paid for by a donation to the Carroll Township Action Group revealed the buildings did not comply with zoning regulations.

After reviewing the third party survey, officials agreed to have their own survey conducted to further investigate the discrepancies.

The township’s survey varied from the action group’s, but it also found that the properties as they stood post-construction did not meet the setback requirements and did not coincide with renderings of the building that were originally submitted.

A variance request that would have allowed the properties to fall out of setback requirements was denied in January.

Supervisors unanimously approved an amendment to current zoning requirements, specifically regarding the permitting process and setback requirements, in April. BLG applied for a new building permit in May to resume work, which really meant backtracking in order to be able to move the already constructed homes within the setback requirements of the township and follow new processes and regulations in place from the approved amendment.

Zoning Officer Jordan Cooper provided an update on the progress last month as work resumed at the site.

According to Cooper, BLG owner AJ Jasim submitted a plan that meets all 11 requirements of the ordinance in May.

His newly requested building permit was granted in a phased approval.

The first phase of approval allowed BLG to dig new footers and other concrete work to reconfigure the foundation of each home.

So far, that’s all that has received approval, and based on inspection reports crews have complied with all township regulations.

“I checked in and the foundation trenches were inspected, the footers were inspected, they were poured and those were inspected as well, so that is the current update,” Cooper said.

BLG has applied for the permits, but has not yet met the requirements to have it approved for the next phase.

“He has not received approval to move the buildings as he did not have an on-site inspector to oversee the actual moving of the structures,” Cooper said. “He has an engineer’s drawing stamped plan to move them, but he did not yet have the required on-site inspector that’s going to have to be there to sign off on what’s happening in real time.”

Some residents question the inspections that were already completed, which are being signed off on by two sets of people including the township’s building inspector.

“There are multiple inspections,” Cooper said. “So one they came to look at the trenches to make sure the depth and width were correct, another for the footer inspection and another once it is poured. So certainly, they are not cutting him any breaks. From what I understand they are holding him to the Pennsylvania (Uniform Construction Code).”

Chairman Ken Hillman said next a report will be submitted to the township for the plan to move the homes and once BLG selects an on-site inspector, the permit to move the structures will be reviewed.

“In order to issue a building permit to move the structures, a report that is designed by an engineer and certified will be submitted,” Hillman said. “Either the person who prepares that report or another person who is certified to oversee the moving of the structures will be on site, but there won’t be a building permit issued for that until all of the information has been provided to us and approved.”

Elizabeth Forward Class of 2026 celebrates graduation
Latest News, Main
June 11, 2026
Elizabeth Forward High School hosted commencement Wednesday at Warrior Stadium for the Class of 2026. Graduates Mya Morgan, Claire Elizabeth Balint, Taelor Paige Kennedy and Edward Denney are shown si...
McKeesport Area OKs final budget with no tax increase
Latest News, Main
By LADIMIR GARCIA lgarcia@yourmvi.com 
June 11, 2026
The school board also approved to begin the design phase of a proposed renovation project at the high school. During a contentious voting meeting Wednesday, the McKeesport Area School Board unanimousl...
Elizabeth Township to host 4-day America250 celebration
Latest News, Main
By SARAH PELLIS spellis@yourmvi.com 
June 11, 2026
The celebration is set for June 25-28 throughout Elizabeth Township. Elizabeth Township will celebrate America’s 250th anniversary celebration with a weekend full of events, and many involved in the f...
Rockin’ on the Mon Riverfest to heat up the aquatorium
Entertainment, Latest News, Main
June 11, 2026
Sponsored by the Washington County Tourism Promotion Agency the third annual event is set for June 20. By MATT PETRAS For the MVI The third annual Rockin’ on the Mon RiverFest returns to the Noble J. ...
Reschenthaler secures $200M for Southwest Pa.
Around The Valley, Latest News, Main
June 11, 2026
Projects that will impact the Mon Valley got a slice of the federal Community Project Funding. By the MVI Several projects that will impact the Mon Valley will receive a share of $34.5 million in fede...