For more than a decade, Rostraver Township officials have pushed for improvements to the Interstate 70 and Route 201 interchange, where traffic congestion, safety concerns and an aging railroad overpass have complicated efforts to find a solution.
Now, PennDOT is taking a closer look at the corridor, but officials cautioned Wednesday that the ongoing study does not mean construction is on the horizon.
Representatives from the Pennsylvania Department of Transportation met with residents and local officials at Belle Vernon Area High School Wednesday to discuss a Planning and Environment Linkages (PEL) study examining transportation needs along the heavily traveled corridor.
The study, which began in June 2025, is intended to identify problems, evaluate potential solutions and gather public input before determining whether improvements should advance as future construction projects.
PennDOT District 12 Executive Rachel Duda said the department is working to understand the area’s needs, including traffic patterns, environmental features, property impacts and community concerns.
“Right now we’re here for the I-70 Route 201 interchange study, and what we’re doing here is to get information from the public so that we can continue to study the area and see what the needs are,” Duda said.
Duda said the interchange presents unique challenges because of the amount of development and traffic surrounding it.
“This one is unique because of how congested this area is,” she said, explaining that traditional interchange designs might not work without affecting nearby businesses and other destinations.
Newer interchange and intersection configurations could offer possibilities that were not available when improvements were previously considered.
The study area includes the I-70/Route 201 interchange, just over a mile of Route 201 between Vance Dei Cas Highway and the Westmoreland/ Fayette county line, and approximately 2.8 miles of I-70 from Exit 41 at Route 906 to the bridge carrying I-70 over the Wheeling and Lake Erie Railroad.
The study must also account for several physical and environmental constraints, including existing bridges, railroad structures, St. Mary’s Cemetery and the nearby roadway network.
Longstanding concerns
For Rostraver Township officials, the study represents progress after years of pushing for improvements, but they are not convinced the potential solutions presented so far will adequately address the corridor’s problems.
Township Commissioner Devin DeRienzo, vice chairman of the board, said officials were previously told other portions of the I-70 modernization effort needed to be completed before attention could turn to Route 201.
“We’re happy about it. Very happy about it, actually,” De-Rienzo said.
Still, he and township Planner Tamira Spedaliere said they have not been sold on some of the potential improvements presented.
DeRienzo is particularly concerned about the railroad overpass, which he believes must be addressed for any improvements to be effective.
“At the end of the day, if they don’t do anything with the railroad trestle, you might as well not do anything,” he said.
Spedaliere, who said she has spent 25 years seeking funding for improvements, questioned whether a roundabout would adequately address congestion.
“A roundabout is what they’re talking about doing is not going to solve the congestion problem,” she said. “It’s just going to alleviate a traffic light, but you’re still going to be funneling up.”
Her concerns reflect problems identified in PennDOT’s traffic analysis, which found that closely spaced intersections and limited space for vehicles waiting at signals can cause backups and gridlock.
PennDOT has also presented conceptual illustrations showing different roadway and ramp configurations, including wider shoulders, grassy medians and concrete barriers.
No roundabout, interchange configuration or other improvement alternative has been formally selected.
Information presented Wednesday outlined several problems throughout the study area.
Approximately 30,000 vehicles travel I-70 through the corridor daily, with trucks accounting for an estimated 25% to 30% of that traffic.
According to the study team, the high percentage of commercial vehicles creates additional challenges because trucks require more time and distance to accelerate, slow down and maneuver.
An analysis of crashes over a five-year period identified Route 201 south of the interchange as an area with a high concentration of crashes.
The intersection of Route 201 and Vance Dei Cas Highway was also identified as a concern because its complicated configuration may contribute to driver confusion.
Other deficiencies include inadequate stopping sight distances, short acceleration and deceleration lanes, steep grades, narrow shoulders and insufficient clearance beneath some bridges.
Traffic modeling identified congestion at several intersections along Route 201, particularly during peak travel periods.
Because the intersections are close together, backups can extend from one intersection to another, creating gridlock. Traffic waiting to exit I-70 can also extend toward the interstate.
Projections through 2055 suggest those conditions could worsen without improvements, particularly during peak shopping periods or when crashes, detours or traffic signal problems disrupt traffic flow.
The study also identified significant gaps in pedestrian access along Route 201, where businesses, restaurants and shopping centers attract people traveling on foot.
Despite that activity, there are no sidewalks along the corridor. During field observations, pedestrians were seen walking along roadway shoulders, crossing Route 201 between driveways and traveling through grassy areas between businesses.
“I don’t think people realize how many pedestrians are walking along,” Spedaliere said.
Stephanie Lee, operations coordinator for the Mid Mon Valley Transit Authority, said the lack of pedestrian accommodations also creates challenges for transit riders.
She said passengers frequently travel between businesses along Route 201, including Walmart and nearby shopping destinations.
The transit authority provides free transportation for some short trips between businesses, but pedestrian activity remains common.
Lee said buses have also been involved in collisions with vehicles pulling out of businesses along the corridor.
She questioned whether changes to driveway access or the addition of service roads could help reduce conflicts.
The study team also noted that buses must load and unload passengers in the Walmart parking lot because Route 201 lacks adequate shoulders or designated bus pull-offs.
What happens next
PennDOT officials emphasized that the PEL study is a planning process, not an approved construction project.
The study team has completed initial data collection, fieldwork and technical assessments and is working to establish transportation needs before developing potential solutions.
Those alternatives would be evaluated based on safety, traffic performance, environmental impacts, feasibility and community concerns.
Any future projects would still require separate development, environmental review, design and funding before construction could begin.
Ken Rich, a senior public involvement specialist and facilitator with McCormick Taylor Inc., said the study could eventually lead to one large project, several smaller projects or improvements completed in phases.
But none of those decisions has been made.
PennDOT also plans to establish a community stakeholder committee with representatives from local government, emergency services, education, businesses, industry, transit agencies and residents.
Residents interested in serving can submit an interest form for consideration.
Public comments on the study and applications for the stakeholder committee will be accepted through Oct. 28.
For more information, to submit a public comment or to complete a community stakeholder committee interest form, visit www.i-70projects. com.