Elizabeth Township commissioners, residents respond to data center report
Latest News, Main
October 6, 2026

Elizabeth Township commissioners, residents respond to data center report

By SARAH PELLIS spellis@yourmvi.com 

A town hall meeting to address questions from the community has been scheduled for Oct. 13.

After records made public Monday about discussions of a possible data center in Elizabeth Township, commissioners and area residents addressed the issue during Monday’s meeting.

An Eastern Pennsylvania developer wants to build a 1-gigawatt data center campus and natural gas plant in rural Elizabeth Township at a former landfill site, according to email records obtained by Pittsburgh’s Public Source.

The development, located at a 549-acre parcel on Henderson Road near the Youghiogheny River, would include anywhere from 11 to 28 two-story data center buildings powered by a combined cycle generator. The site could generate $125 million in tax revenue for the municipality and Elizabeth Forward School District.

The site is currently owned by Buena Vista Solar, which purchased the “Fiore Property” in 2022 for $1. A former U.S. Steel landfill site, it was once considered as a potential location for a now-canceled power plant.

Tim Hendricks, a resident of New Hope in Bucks County, wants to develop the site through his company Hendricks Group Developers, LLC, according to records obtained by Public Source. Hendricks asked to make a proposal to the commissioners regarding the idea.

Hendricks said in an email that around 220 acres of the site are “not contaminated.”

Commissioner Adam Musisko said Monday that he wanted to clear up misinformation that was circulating online.

Musisko said the township was initially approached in June by Hendricks. An hour-long committee meeting was held July 9 where they discussed what he was proposing and how it would affect the township.

In a statement released Monday, state Rep. Andrew Kuzma, R-Elizabeth Township, said he and commissioners were approached by Hendricks in the past few weeks.

On July 27, the committee met again, with Hendricks revised some of his answers to questions, according to Musisko, who said the meeting lasted about 30 minutes.

“We still had many questions, but we were scratching our heads with some misconceptions, and things we didn’t know about data centers,” Musisko said. “We didn’t know that much. Considering the volatility of the subject, the committee stopped that meeting about 30 minutes in, and said ‘Hold on a minute. Will you present this to our township?’” According to Musisko, there are accusations that they have been learning about data centers for months. He stated that the committee only discussed data centers for a total of 90 minutes over the two meetings.

He added that there were no more meetings or discussions about data centers after July 27. A town hall request was made right after the meeting, but Musisko said it takes months to plan.

“This proposal is in its infancy, but the board elected to involve the community at the very beginning of any potential development of something as potentially polarizing as a data center,” Musisko said. “This is the most front-door deal there’s ever been. The guy approached us, and we said ‘Hold on. This is too volatile, let’s talk with our community.’ Nothing is being hidden. In fact, it’s quite the opposite.”

Many members of the public argued that commissioners should have told the public about the potential of a data center when the township was initially approached in June.

Resident Kellianne Frketic said during public comment that the residents deserve transparency, citing the June discussion for when the township received initial detailed communications from Hendricks and the initial proposal describing the project and data centers.

“The Right to Know records tell a very different story. There were subsequent discussions after (the meeting),” Frketic said. “Calls, revised site plans and additional meetings. On Sept. 4, he told the township manager that (Hendricks) had further details to pass along to the commissioners for their details. Sept. 14, (Hendricks) reported that he had spoken extensively with Commissioner (Josh) Walls on Labor Day, and described that call as ‘A good one.’ That is an ongoing conversation between the developer and township officials about proposal development.”

Data center developments across the country have encountered pushback from local residents concerned about noise and their water and electricity usage.

Communities around the Mon Valley are taking action, with many local governments passing moratoriums to pause any data center development, giving local officials time to review and strengthen their ordinances before any future data center proposal can move forward.

Allegheny County Council unanimously voted to ban large data centers on county-owned property last month as municipalities contemplate or implement data center construction moratoriums.

Gov. Josh Shapiro signed an executive order this summer requiring data centers to follow stricter environmental and transparency standards. Under the order, developers have to pledge to abide by certain clean energy and job creation requirements.

Kuzma cited in the recently passed House Bill 2496, which allows municipalities a 180-day pause on data- center applications to update zoning.

Resident Sandy Hearn said the township should adopt a resolution to establish a temporary pause on data centers until it has an ordinance in place, and that all data center development applications should be rejected until an ordinance is established.

“We should have a survey from all township residents on this very important issue. We should work on, then draft, then adopt a data center ordinance,” Hearn said. “Then, there would be discussions with data center developers to see if they are a fit with our township and align with our ordinances. Elizabeth Township should reject all nondisclosure agreements with data center developers.”

According to Musisko and Kuzma, there are no plans or any kind of building permit applications filed with the township for the project.

On Sept. 15, President Josh Walls announced at a commissioners meeting that Elizabeth Township had been approached about a data center project.

Commissioners voted Monday to hold a town hall meeting at 6 p.m. Oct. 13 in the Elizabeth Forward Middle School auditorium to discuss the center.

“As a resident of Mt. Vernon and native of Buena Vista, I am concerned about the possibility of noise, utility rate hikes and environmental impacts,” Kuzma said. “While I will be attending the town hall meeting with an open mind, my position will ultimately be the same as my neighbors and the majority of township residents, as I am their representative.”

Many argued online that the meeting is only for curated questions, and Musisko said it needs to be structured so there are data and charts provided to answer questions from the public. He added that the town hall allows the community to ask questions and learn more about what data centers are.

Commissioners will sit with the audience during the meeting. It will bemoderated by resident Eric Piper after resident Chad Licht was unable to moderate. Musisko said they wanted someone impartial to ask difficult questions.

“We’re optimistic that we are going to have a civil meeting that can provide clarity to all the questions, particularly the hard ones,” Musisko said. “It is up to the moderator how they are going to share that. This is not a presentation from the developer. It is our community assembling all the questions we have about data centers, asking them on our terms, in front of everybody.”

Hearn said that if the township is looking to bring people into the township, data centers will keep them away.

“The residents of Elizabeth Township should decide if they want a data center in their community,” Hearn said. “Local officials have a responsibility to communicate openly and honestly with the community. They represent the residents, not the developers.”

Clairton band brings out the Bears
Latest News, Main
November 14, 2026
The Clairton High School marching band performs as the Bears football team takes the field before kickoff of Friday’s WPIAL Class 1A quarterfinal matchup with California at Russ Grimm Field at Southmo...
California company destroyed by fire
Latest News, Main
November 14, 2026
No injuries were reported in the Maund Industries blaze, but the building and the equipment inside were ruled a total loss. By the MVI A massive fire and multiple explosions Thursday night destroyed M...
Plans unveiled for ‘McKeesport Tomorrow’ project
Latest News, Main
By By THOMAS LETURGEY For the MVI 
November 14, 2026
It includes strong investment along the city’s riverside. In November 2025, McKeesport leaders and representatives from The Collaborative, an urban planning organization from Boston, started talking w...
GoFundMe set up for Monessen fire victim
Latest News, Main
By SARAH PELLIS spellis@yourmvi.com 
November 14, 2026
Alexa Lepresti’s dog is receiving veterinary care after being rescued. A fundraiser has been started for a Monessen resident whose house was badly damaged by fire. Monessen firefighters rescued Alexa ...
Donora approves sale and demolition of properties
Around The Valley, Latest News, Main
By MICHAEL VINSICK mvinsick@yourmvi.com 
November 14, 2026
The purchase of 700 Meldon Ave. will lead to a new location for Dollar General. Donora Council selected bidders to sell one property and demolish another during Thursday’s meeting. Council unanimously...
Groundbreaking today for credit union in Elizabeth Borough
Latest News, Main
By SARAH PELLIS spellis@yourmvi.com 
November 14, 2026
Steel Strong is moving to the former Rite Aid location in Elizabeth Borough. An old building is getting new life in the Mon Valley. The former Rite Aid at 300 Market St. in Elizabeth Borough was purch...