Turnpike provides updates on Expressway projects
Around The Valley, Latest News, Main
May 4, 2026

Turnpike provides updates on Expressway projects

By SARAH PELLIS spellis@yourmvi.com 

It will cover 68 miles when all 7 sections are complete.

Several new Mon/Fayette Expressway updates are in progress this week.

The expressway currently stretches 54 miles from I-68 near Morgantown, W.Va., to PA Route 51 in Jefferson Hills. Once all seven sections are complete, the Expressway will extend 68 miles to Interstate 376 in Monroeville.

Construction is currently underway on the third section of the southern portion, which runs from Route 51 in Jefferson Hills to Route 837 in Duquesne.

Section 53A1

Work on Section 53A1, which begins where the current expressway ends at Route 51 in Jefferson Hills and stretches approximately three miles north of Coal Valley Road, has been ongoing since March 2023. It is projected to end this fall.

The nearly $214 million contract requires Trumbull Corp. to excavate more than four million cubic yards of earth and build six bridges. The remaining construction sections will go through the bidding process and begin construction as bids are awarded.

The standard work shift is 6 a.m. to 4:30 p.m. Mondays to Thursdays, with Friday/ Saturday shifts used when needed.

Coal Valley Road is open again as construction is moving forward with the Expressway, construction engineers stated in the Pennsylvania Turnpike Commission’s Monday update.

Coal Valley Road was closed for up to two months for road and slope reconstruction and another three to four weeks for continued slope restoration work.

The road will not close again, according to Pennsylvania Turnpike consultant Craig White.

Southbound drivers on Route 43 will use the southbound ramp, while northbound drivers will cross over to the southbound side to Jefferson Boulevard. The Turnpike stated that drivers should monitor speed and stay in their lane through the construction area.

For construction on Route 51, drivers are advised to follow traffic signs, arrows, merging areas, stop and yield signs. Lane closures will happen northbound and southbound during non-peak hours for sign installations.

Section 53A2

Section 53A2 of the southern section begins just north of Coal Valley Road and runs about two miles north of Camp Hollow Road (State Route 2043) near Curry Hollow Road in West Mifflin.

The Turnpike Commission awarded Trumbull Corporation the $165.6 million contract in October 2023, and construction is scheduled to finish in the summer of 2027.

The contract requires Trumbull to excavate approximately 3.7 million cubic yards of earth and build five bridges. A full interchange at Camp Hollow Road will also be constructed under the terms of the contract, along with two roundabouts on Camp Hollow Road.

The intersection of Lebanon Church Road and Camp Hollow Road has started going on during the 2026 construction season, as advance utility work in the area continues, and utility relocation is underway now.

New England Road and Lower Camp Hollow Road are now open, and roadway sections will be rebuilt this year. The Turnpike advised drivers that there may be daylight lane closures with flaggers and alternating traffic for both areas.

On Upper Camp Hollow Road, northbound and southbound traffic are in the new roadway alignment and the roadway is completed. Access to Lebanon School Road is open and access to Lebanon Manor is via Beverly Drive.

Section 53A2 is to be finished in the summer of 2027, according to the PA Turnpike’s website.

Section 53B1A

On Jan. 13, the Turnpike awarded Trumbull Corp. a $163.5 million contract to build the third section (53B1A), and preliminary work is going on for when full construction begins.

The section will extend approximately 1.5 miles beginning just north of the Camp Hollow Road (State Route 2043) roundabouts in West Mifflin and run north where it will tie in with a new interchange at Pittsburgh McKeesport Boulevard (State Route 2045) near the Richland Cemetery in Dravosburg.

“This project is basically picking up where the prior section left off,” senior project manager Eric Buchan said in February. “Essentially this project carries PA 43 toward Kennywood to Pittsburgh McKeesport Boulevard. This project completes all the work in between. Bridges, roadway, earth moving to complete that connection.”

The contract requires Trum- bull to excavate approximately 1.5 million cubic yards of earth, construct two noise walls and build four bridges. A projected end date is approximately October 2029, according to Trumbull project manager Pat Daley.

For the future of this section on Camp Hollow Road, construction traffic will enter and exit Camp Hollow near the new roundabouts. Construction traffic will also enter and exit at the entrance of Pitt McKeesport Boulevard.

Some deliveries and construction traffic will be on Curry Hollow Road near the West Mifflin SSA Pump Station.

Tree clearing and stump grinding mostly completed as the Turnpike is placing erosion control measures including diversion ditches, silt sock, rock dams and silt sock ponds. They are also stockpiling quarry rock for embankment construction, and constructing rock toes for embankments.

More updates on the construction can be found on the PA Turnpike Commission’s website every week at www. paturnpike. com.

Main
May 9, 2026
Find out what happens over the weekend in Monday’s electronic edition of the MVI.
Family honors mom’s legacy of kindness by continuing her bracelet ministry
Main
By TAYLOR BROWN, Senior Reporter 
May 9, 2026
Before her passing last year, Hazel Brock Rone began making bracelets and giving them away to spread kindness and love. At Anthony E. Madison Sr. Veterans Memorial Park in Monessen, Valerie Osborne st...
BVA’s mock prom crash confronts real-life consequences
Main
By LADIMIR GARCIA lgarcia@yourmvi.com 
May 9, 2026
About 400 Belle Vernon Area students attended the annual drill to raise awareness of driving impaired. On Friday, hundreds of Belle Vernon Area High School students stood in silence as they watched fi...
Main
May 9, 2026
The Senate bill faces much stiffer odds in the Democratic-majority state House. By Pennlive.Com The state Senate this week passed a bill that would end Pennsylvania’s emissions inspection program for ...
The bracelets were no longer just crafts or keepsakes
News
May 9, 2026
The bracelets were no longer just crafts or keepsakes. They had become reminders of the woman who started them and the kindness she spent a lifetime showing others. And, that’s how the Be Kind Ministr...