Turnpike provides updates on Expressway projects
Around The Valley, Latest News, Main
May 4, 2026

Turnpike provides updates on Expressway projects

By SARAH PELLIS spellis@yourmvi.com 

It will cover 68 miles when all 7 sections are complete.

Several new Mon/Fayette Expressway updates are in progress this week.

The expressway currently stretches 54 miles from I-68 near Morgantown, W.Va., to PA Route 51 in Jefferson Hills. Once all seven sections are complete, the Expressway will extend 68 miles to Interstate 376 in Monroeville.

Construction is currently underway on the third section of the southern portion, which runs from Route 51 in Jefferson Hills to Route 837 in Duquesne.

Section 53A1

Work on Section 53A1, which begins where the current expressway ends at Route 51 in Jefferson Hills and stretches approximately three miles north of Coal Valley Road, has been ongoing since March 2023. It is projected to end this fall.

The nearly $214 million contract requires Trumbull Corp. to excavate more than four million cubic yards of earth and build six bridges. The remaining construction sections will go through the bidding process and begin construction as bids are awarded.

The standard work shift is 6 a.m. to 4:30 p.m. Mondays to Thursdays, with Friday/ Saturday shifts used when needed.

Coal Valley Road is open again as construction is moving forward with the Expressway, construction engineers stated in the Pennsylvania Turnpike Commission’s Monday update.

Coal Valley Road was closed for up to two months for road and slope reconstruction and another three to four weeks for continued slope restoration work.

The road will not close again, according to Pennsylvania Turnpike consultant Craig White.

Southbound drivers on Route 43 will use the southbound ramp, while northbound drivers will cross over to the southbound side to Jefferson Boulevard. The Turnpike stated that drivers should monitor speed and stay in their lane through the construction area.

For construction on Route 51, drivers are advised to follow traffic signs, arrows, merging areas, stop and yield signs. Lane closures will happen northbound and southbound during non-peak hours for sign installations.

Section 53A2

Section 53A2 of the southern section begins just north of Coal Valley Road and runs about two miles north of Camp Hollow Road (State Route 2043) near Curry Hollow Road in West Mifflin.

The Turnpike Commission awarded Trumbull Corporation the $165.6 million contract in October 2023, and construction is scheduled to finish in the summer of 2027.

The contract requires Trumbull to excavate approximately 3.7 million cubic yards of earth and build five bridges. A full interchange at Camp Hollow Road will also be constructed under the terms of the contract, along with two roundabouts on Camp Hollow Road.

The intersection of Lebanon Church Road and Camp Hollow Road has started going on during the 2026 construction season, as advance utility work in the area continues, and utility relocation is underway now.

New England Road and Lower Camp Hollow Road are now open, and roadway sections will be rebuilt this year. The Turnpike advised drivers that there may be daylight lane closures with flaggers and alternating traffic for both areas.

On Upper Camp Hollow Road, northbound and southbound traffic are in the new roadway alignment and the roadway is completed. Access to Lebanon School Road is open and access to Lebanon Manor is via Beverly Drive.

Section 53A2 is to be finished in the summer of 2027, according to the PA Turnpike’s website.

Section 53B1A

On Jan. 13, the Turnpike awarded Trumbull Corp. a $163.5 million contract to build the third section (53B1A), and preliminary work is going on for when full construction begins.

The section will extend approximately 1.5 miles beginning just north of the Camp Hollow Road (State Route 2043) roundabouts in West Mifflin and run north where it will tie in with a new interchange at Pittsburgh McKeesport Boulevard (State Route 2045) near the Richland Cemetery in Dravosburg.

“This project is basically picking up where the prior section left off,” senior project manager Eric Buchan said in February. “Essentially this project carries PA 43 toward Kennywood to Pittsburgh McKeesport Boulevard. This project completes all the work in between. Bridges, roadway, earth moving to complete that connection.”

The contract requires Trum- bull to excavate approximately 1.5 million cubic yards of earth, construct two noise walls and build four bridges. A projected end date is approximately October 2029, according to Trumbull project manager Pat Daley.

For the future of this section on Camp Hollow Road, construction traffic will enter and exit Camp Hollow near the new roundabouts. Construction traffic will also enter and exit at the entrance of Pitt McKeesport Boulevard.

Some deliveries and construction traffic will be on Curry Hollow Road near the West Mifflin SSA Pump Station.

Tree clearing and stump grinding mostly completed as the Turnpike is placing erosion control measures including diversion ditches, silt sock, rock dams and silt sock ponds. They are also stockpiling quarry rock for embankment construction, and constructing rock toes for embankments.

More updates on the construction can be found on the PA Turnpike Commission’s website every week at www. paturnpike. com.

Support pledged for Mon View Heights residents
Latest News, Main
By SARAH PELLIS spellis@yourmvi.com 
May 6, 2026
The apartment complex in West Mifflin is accused of providing substandard living conditions. West Mifflin Councilwoman Carla Payne-Harrison held a community meeting Tuesday evening to discuss the opti...
Proposed bill would charge municipalities that rely on state police for coverage
Latest News, Main
Fallowfield Township considers police options
By TAYLOR BROWN, Senior Reporter 
May 6, 2026
Pa. lawmakers could make the cost of relying on state police far more expensive. A proposal in Harrisburg that could eventually require municipalities to pay for Pennsylvania State Police coverage is ...
3 UPMC hospitals at risk of closure from Medicaid cuts
Latest News, Main
May 6, 2026
UPMC McKeesport was among the facilities mentioned in a report compiled by Public Citizen. By JACK TROY TribLive Three UPMC hospitals in Southwestern Pennsylvania are at risk for closure as President ...
Local lawmakers support removing cell phones from classrooms
Latest News, Main
By LADIMIR GARCIA lgarcia@yourmvi.com 
May 6, 2026
A bill was approved last week by the House Education Committee. A bipartisan bill to restrict cell phone use in Pennsylvania schools passed through the state House Education Committee last week, movin...
Pa. American Water plans $.1.1M upgrade to Elizabeth Township water system
Around The Valley, Latest News, Main
May 6, 2026
Pennsylvania American Water representatives met with Elizabeth Forward School District officials prior to the start of the project to coordinate work. By the MVI Pennsylvania American Water recently b...
Saints Joachim and Anne Catholic Parish celebrate Confirmation
Features, Latest News, Main
May 6, 2026
Saints Joachim and Anne Catholic Parish of Elizabeth/Glassport/Liberty Borough, celebrated the Sacrament of Confirmation on April 28 at the St. Eugene Campus in Liberty Borough with Bishop Mark Eckman...