Elizabeth Forward School Board updated on construction
A representative of McLean Architects said work on Phase 1 is about one-third complete.
David McLean of McLean Architects updated the Elizabeth Forward school board about the high school renovations this week.
McLean said they are roughly a third of the way through the project, estimating that about 31% is complete.
With $60.2 million budgeted for construction, the project has a contingency of 5% percent or around $3 million.
McLean said 10.26% of the contingency has been used so far, which is an in...