Q&A session set on final phase of river project

By Mon Valley Independent

By TAYLOR BROWN

Senior Reporter

tbrown@yourmvi.com

More questions will be answered at a May 16 public meeting as the U.S. Army Corps of Engineers prepares to enter the final phase of its Lower Monongahela River Project. 

The project, nearly 30 years in the making, includes construction of the larger lock chamber at Locks and Dam 4 at river mile 41.5 near Charleroi and the replacement of the fixed-crest dam with a gated dam at Locks and Dam 2 in Braddock.

It also includes a $30 million contract with Joseph B. Fay Company of Pittsburgh to remove the Monongahela River Locks and Dam 3 in Elizabeth, which is the project’s next and final phase. 

The work under the new contract involves a controlled removal of the locks and dam to equalize the upstream and downstream river levels. 

Corps contractors will remove the locks and dam concrete debris and repurpose it to stabilize the facility’s land wall and dam abutment, which will remain in place.

The Corps of Engineers has held past public meetings to help keep residents informed as the process moves forward.

The meeting will take place at 7 p.m. at Elizabeth Forward High School to help the community learn more about the project’s progress and future while alleviating any concerns. 

It will be an hour-long presentation and question-and-answer session. 

Steve Fritz, the district’s mega project program manager, said meetings of this type play a vital role when it comes to large projects. 

“Public meetings are important opportunities for communities to learn about, provide feedback, voice concerns and share information about district activities and objectives,” Fritz said. 

Locks and Dams 2, 3 and 4 on the Monongahela River in Allegheny, Washington and Westmoreland counties are the oldest three operating navigations facilities on the river. 

At one point, they saw the highest volume of commercial traffic on the entire Mon navigation system.

Locks and Dam 3 in Elizabeth have been operating since 1907, but the facility is prone to flooding and must therefore be shut down during high-water events. 

Removing the dam will create a continuous pool of riverway stretching 30 miles, which will provide a lot of opportunity for communities and residents who use the river for recreation. 

After the presentation, stations will be set up for community members to speak with district experts one-on-one about topics such as the history, status, river levels, impact to personal property and what to expect as start dates gets closer. 

“Many of the navigation improvements made on our rivers go unnoticed by residents and communities bordering the river,” Fritz said. “However, there will be noticeable changes to river levels in the summer of 2024.” 

District contractors will begin bringing down the dam the week of July 8 using explosives to control demolition. 

The district will restrict navigation near Elizabeth for at least three days. Work to remove the dam entirely will continue through the end of the year.

“Our primary concern is maintaining safe navigation throughout the demolition phase,” Fritz said.

Until the entire dam is removed, and until the Corps verifies the navigation channel is safe through that area, all traffic will have to continue to go through the lock.  

The Pittsburgh District will begin to remove the lock chamber walls next year, and the project is expected to last until 2027.

Removing the dam will raise the river’s water levels by approximately 2 feet for communities between Elizabeth and Braddock. 

The river elevation will drop by approximately 3.2 feet between Elizabeth and the dam in Charleroi. 

Demolition will result in the pool level reaching 723.7 feet between Charleroi and Braddock.

Work has been done since 1994 to modernize locks 2, 3 and 4 on the lower Mon in Braddock, Elizabeth and Charleroi with more than $1 billion in investments from the federal government to do so.

It started with an initial phase in 2004 that included major work at Locks and Dam 2 in Braddock before moving on to renovations of Locks and Dam 4 in Charleroi, which was recently completed.

Removing Locks and Dam 3 in Elizabeth is the final phase. 

“This signifies the culmination of 30 years of engineering and contracting efforts to modernize the navigation facilities on the lower Monongahela River,” Fritz said. “In addition to providing reliable river navigation for the next century, this project will return more than $200 million in annual benefits to the region and nation.” 

For more information on the project, visit https://www.lrp.usace.army.mil/Missions/Planning-Programs-Project-Management/Key-Projects/Lower-Mon-Project.

Graduation day at PennWest California
Latest News, Main
December 15, 2025
Hannah Smith, an elementary education major from Cecil, celebrates with fellow graduates during PennWest California’s Fall 2025 commencement ceremony Saturday at the Convocation Center. See more photo...
BVA investigating social media threats
Latest News, Main
December 15, 2025
In response, police will have an increased presence today at Rostraver Elementary. By LADIMIR GARCIA and TAYLOR BROWN lgarcia@yourmvi.com tbrown@yourmvi.com Belle Vernon Area School District officials...
Up to 6 inches of snow blankets the Mon Valley
Latest News, Main
By TAYLOR BROWN, Senior Reporter 
December 15, 2025
The storm was followed by bitter cold, but a warmup is in the forecast for later this week. Snow from a weekend winter storm tapered off early Sunday morning, but not before dropping several inches ac...
Latest winners honored in Ideas 2 Enterprise program
Latest News, Main
By TAYLOR BROWN, Senior Reporter 
December 15, 2025
Hannah Widdifield of Simple String Studio won first-place honors and a $5,000 grant. Big ideas and small businesses were in the spotlight Thursday as local entrepreneurs gathered to celebrate the late...
Carnegie Free Library of McKeesport has new director
Around The Valley, Latest News, Main
December 15, 2025
Michael Chirichella wants people to feel at home whenever they visit the library. By COLETTE FUNCHES McKeesport Community Newsroom When visitors enter the doors of the Carnegie Free Library of McKeesp...
Elizabeth Township sets water shut-off procedure
Around The Valley, Latest News, Main
By SARAH PELLIS spellis@yourmvi.com 
December 15, 2025
It runs through March 31, covering non-payment issues for the winter. Elizabeth Township has approved a water shut-off procedure with Pennsylvania American Water for customers who don’t pay their bill...